The station will be placed on a 12.2-kilometer bypass of Bien Hoa City that will start at Tra Co Church in Trang Bom District and end at National Highway 51 in Bien Hoa City.
As scheduled, vehicles with less than 12 seats will pay a toll fee of VND20,000 until December 31, 2015 and VND35,000 from January 1, 2016. Those vehicles from 12 to 30 seats will pay VND30,000 and VND50,000 and vehicles with 31 seats or more pay VND44,000 and VND75,000 respectively.
Meanwhile, trucks weighing 18 tons or more will be subject to toll fees between VND80,000-VND160,000 until late 2015 and between VND140,000-VND200,000 from January 1, 2016.
The bypass project is being developed under build-operate-transfer (BOT) format with a total cost of VND751 billion. Last year, the Ministry of Transport approved the expansion of the road from four to six lanes with an additional investment of VND75 billion.
The project is expected for completion in April. The investor, Dong Thuan Investment Joint Stock Company, estimates to recover capital by collecting toll fees over nearly 24 years.
The project aims to help reduce traffic congestion in inner Bien Hoa City and facilitate traffic to the Central and the North.
In addition, the new Dong Nai bridge project will have two approach roads completed in June 2014. Toll collection for the project will start on July 1.